Architectural Drawing of the Project Project Details Current Picture
Name of the project: PUBLIC FAIR RE DEVELOPMENT PROJECT AT ANURADHAPURA STAGE II
Province: North Central
Town: Anuradhapura
Investment: Rs.85.6Mn
Public Benefit:
Date of Commencement:18.04.2018
Date of Completion: 31.03.2019 (On going)
Name of the project: PUBLIC FAIR REDEVELOPMENT PROJECT AT ANURADHAPURA STAGE I
Province: North Central
Town: Anuradhapura
Investment: Rs.90.85Mn
Public Benefit:
Date of Commencement:September 2017
Date of Completion:31.03.2019 (On going)
Name of the project:MIHINTHALE TOWN CENTER INFARSTRUCTURE DEVELOPMENT STAGE II
Province: North Central
Town: Anuradhapura
Investment: Rs.8.91 Mn
Public Benefit:
Date of Commencement:18.04.2018
Date of Completion: 18.11.2018 (Completed)
Name of the project:MIHINTHALE TOWN CENTER INFRASTRUCTURE DEVELOPMENT (LANDSCAPE PROJECT)
Province: North Central
Town: Anuradhapura
Investment: Rs.5.5 Mn
Public Benefit:
Date of Commencement:September 2017
Date of Completion:Completed
Name of the project:RECREATIONAL FACILITY DEVELOPMENT AT KUMBICHCHANKULAMA,(JOGGING TRACK, CONSTRUCTION OF 03 BRIDGES) STAGE III
Province: North Central
Town: Anuradhapura
Investment: Rs.17.04 Mn
Public Benefit:
Date of Commencement:
25.04.2018
Date of Completion:
Completed
Name of the project:RECREATIONAL FACILITY DEVELOPMENT AT KUMBICHCHANKULAMA,(JOGGING TRACK, CONSTRUCTION OF 03 BRIDGES & TOILET BLOCK) STAGE 1V
Province: North Central
Town: Anuradhapura
Investment: Rs.47.56Mn
Public Benefit:
Date of Commencement:13.09.2018
Date of Completion:31.03.2019
Name of the project: KEKIRAWA TOWN CENTER DEVELOPMENT PROJECT (REMEDYING DEFECTS OF EXISTING MARKET BUILDING AT KEKIRAWA) STAGE II
Province: North Central
Town: Anuradhapura
Investment: Rs.28.72Mn
Public Benefit:
Date of Commencement: 18.04.2018
Date of Completion: 31.03.2019 (On going)
Name of the project:KEKIRAWA TOWN CENTER DEVELOPMENT PROJECT REMEDYING DEFECTS OF EXISTING MARKET BUILDING STAGE I
Province: North Central
Town: Anuradhapura
Investment: Rs.50Mn
Public Benefit:
Date of Commencement: June 2017
Date of Completion:31.03.2019 (On going)
Name of the project:CITY CENTER REDEVELOPMENT PROJECT- THAMBUTHTHEGAMA
Province: North Central
Town: Anuradhapura
Investment: Rs.72.3Mn
Public Benefit:
Date of Commencement: Completed
Date of Completion: 31.03.2019 (Completed)
Name of the project:ELAYAPATHTHUWA TOWN IMPROVEMENT PROJECT
Province:North Central
Town: Anuradhapura
Investment: Rs.45.2Mn
Public Benefit:
Date of Commencement: August 2017
Date of Completion: 20.12.2018 (Completed)
Name of the project:SERVICE ROAD DEVELOPMENT -NOCHCHIYAGAMA
Province:North Central
Town: Anuradhapura
Investment: Rs.55.0 Mn
Public Benefit:
Date of Commencement: July 2017
Date of Completion: 31.03.2019 (Completed)
Name of the project:PROPOSED HARITHA UYANA MULTI-FUNCTIONAL BUILDING AT HOROWPOTHANA
Province: North Central
Town: Anuradhapura
Investment: Rs.29.98 Mn
Public Benefit:
  • Improved leisure and recreational facilities with health improvement
Date of Commencement: 08.11.2018
Date of Completion: 01.05.2019 (On going)
Name of the project:PROPOSED HARITHA UYANA MULTI-FUNCTIONAL BUILDING AT PANDUKABHAYAPURA
Province:North Central
Town: Anuradhapura
Investment: Rs.29.98Mn
Public Benefit:
Date of Commencement:24.01.2019
Date of Completion: 10.07.2019 (On going)
Name of the project:CONSTRUCTION OF DANA SHALAWA AT MIRISAWETIYA
Province: North Central
Town: Anuradhapura
Investment:
Public Benefit:
Date of Commencement:
Date of Completion:
Name of the project:RENOVATION OF SHRINE ROOM AT LANKARAMAYA
Province: North Central
Town: Anuradhapura
Investment:
Public Benefit:
Date of Commencement:
Date of Completion:
Name of the project:CONSTRUCTION OF FACILITY BUILDING AT SRI MAHA BODHI
Province: North Central
Town: Anuradhapura
Investment:
Public Benefit:
Date of Commencement:
Date of Completion:
Name of the project:RENOVATION OF VIHARA MANDIRAYA AT ISURUMUNIYA
Province: North Central
Town: Anuradhapura
Investment:
Public Benefit:
Date of Commencement:
Date of Completion:
Name of the project:RENOVATION OF SANGAWASAYA AT THUPARAMAYA
Province: North Central
Town: Anuradhapura
Investment:
Public Benefit:
Date of Commencement:
Date of Completion: